Has anyone confirmed the full stability of the Somitsо landslide?
During its review of the project, the National Environmental Agency requested additional information concerning the Somitso landslide and associated geological risks. The company subsequently submitted the requested information together with the relevant supporting materials.
The documentation explains that the Somitso landslide is located on the left slope of the Jejora River valley, while all hydrotechnical and infrastructure facilities of the SORGITI 2 HPP are situated on the right bank of the river. Accordingly, construction of the project does not directly affect the Somitso landslide.
Following its review of the submitted information, the National Environmental Agency issued a positive environmental decision for the project and authorized its implementation subject to compliance with the conditions specified in the decision.
Of the 24.94-hectare project area, how much lies within the landslide zone?
The total area of the SORGITI 1 and SORGITI 2 project sites is 24.94 hectares. Of this, the SORGITI 1 project area covers approximately 11.70 ha, while the SORGITI 2 project area covers approximately 13.24 ha.
With regard to the Somitso landslide, the available materials confirm that the main hydrotechnical and infrastructure facilities of SORGITI 2, including the penstock pipeline and the HPP powerhouse, are not located within the landslide body itself or within its immediate area. Accordingly, there is no direct territorial overlap between the project’s main facilities and the landslide body.
In addition, an approximately 900-metre section of the pipeline planned along the right bank of the Jejora River, covering an area of approximately 0.9 ha, does not fall within the Somitso landslide area.
The publicly available documents do not specify how many of the 6,402 trees are walnut trees and how many belong to other species.
According to the forest inventory materials submitted to the LEPL National Environmental Agency and the LEPL National Forestry Agency, a total of 6,402 trees have been recorded within the project area. Of these, 16 are walnut trees, while the remaining 6,386 trees belong to other species.
More specifically, the inventory includes: 4,382 alder trees, 447 hornbeams, 791 willows, 2 beech trees, 16 linden trees, 36 wild cherry trees, 88 wild pear trees, 13 wild apple trees, 5 cherry plum trees, 1 mulberry tree, 15 willow trees, 2 elm trees, 1 poplar tree, 169 acacia trees, 141 oak trees, 175 ash trees, 85 pine trees, 17 spruce trees, and 16 walnut trees.
Trees felled within the framework of the project will initially be temporarily stored within the construction corridor and will subsequently be transferred to the LEPL National Forestry Agency for management. The company will then purchase the timber from the state and provide it to the local population free of charge.
Regarding ichthyofauna: In May 2024, the National Environmental Agency requested the submission of additional information, including because an ichthyological survey map had not been provided and part of the surveys had been conducted under conditions of high river turbidity.
The additional information requested by the Agency was subsequently submitted in the relevant explanatory documentation, in accordance with the requirements set out in the Agency’s Letter No. 21/5416 dated 28 May 2024.
Who owns the land in the construction corridor?
The final shapefiles of the project corridor were submitted to the National Environmental Agency together with the Environmental Impact Assessment (EIA) Report, and the relevant materials are publicly available on the Agency’s website, ei.gov.ge.
In addition, no privately owned land plots have been identified within the construction corridor envisaged by the project.
How much water will remain in the Jejora after the HES plants start operating?
The amount of water abstracted by the hydropower plants will depend on how much water is flowing in the Jejora River at any given time. Accordingly, the amount of water remaining in the river will not be fixed - it will vary depending on the season and natural water availability.
The project provides that at least 28% of the river’s natural flow must remain in the riverbed at the SORGITI 2 water intake section, while at least 25% must remain at the SORGITI 1 water intake section.
These percentages represent minimum thresholds rather than fixed volumes. During periods of higher natural flow, the amount of water in the river will naturally be greater and, accordingly, more water will remain in the riverbed. In all cases, the mandatory environmental flow established by the environmental decision and applicable requirements must be maintained. If monitoring results or requirements imposed by the relevant state authorities indicate that more water needs to remain in the river, the volume of water abstracted by the hydropower plants will be reduced.
Bathing Areas and Use of the River by Local Residents
Within the SORGITI 2 project area, particularly in the section near the village of Pipileti, the river has social and recreational importance for the local population. Following consultations with residents, six locations have been selected where traditional bathing areas are planned to be rehabilitated, new bathing and camping areas developed, and, on a seasonal basis, locations suitable for rafting established.
During the bathing season, the water abstraction regime must be managed in a way that ensures sufficient water remains at these locations for the bathing areas to function effectively. At the same time, the development of bathing areas is an additional social and tourism-related measure and does not replace the obligation to maintain the mandatory environmental flow.
How the River’s Condition Will Be Monitored
An automatic hydrological monitoring station has already been installed on the Jejora River. It will continuously record the river’s water level and discharge - that is, the number of cubic metres of water flowing through the river per second. The data will be stored electronically, making it possible to verify the volume of water in the river on a specific date and at a specific time. The accuracy of the station’s measurements will also be periodically verified using a specialized ADCP device.
The project also provides for:
- shaping the river channel in locations where the flow is currently divided into several branches, in order to better concentrate and safely manage the flow;
- continuous monitoring of biodiversity and ichthyofauna during both the construction and operational phases;
- implementation of fish stocking measures after completion of construction and during operation of the hydropower plants, together with monitoring of their effectiveness;
- periodic reporting to the relevant state authorities;
- review of the water abstraction regime and additional mitigation measures based on monitoring results, if such a need is identified.
The project’s environmental assessment, as well as the measures for the protection of biodiversity and fish, are reflected in the EIA materials and monitoring plans. Following review of these materials, the National Environmental Agency issued a positive environmental decision for the project.
Importantly, protection of the river’s ecological condition does not end with a one-time assessment. The actual condition of the river and the project’s impacts must continue to be monitored during the operational phase through ongoing hydrological and biological monitoring.
Clarify the six bathing-site commitmentsMake the monitoring commitments more concrete
If the information is public, why isn't a short version given to residents?
The main documents related to the SORGITI 1 and SORGITI 2 hydropower cascade project including the Scoping Report, the Environmental Impact Assessment (EIA) Report, and the non-technical summary of the EIA Report have been publicly available on the website of the LEPL National Environmental Agency, ei.gov.ge, since 17 November 2023.
In addition, to provide local residents with project-related information in a simpler and more concise format, a dedicated information package is being prepared covering frequently asked questions, key project issues, and the commitments undertaken by the company. This material will be made
Socio-Economic Benefits
Who owns the hydropower plants?
The hydropower plants are directly owned by Regional Renewable Energy Company.
The company’s shareholding structure is as follows: 90% is owned by Racha Green Energy, while 10% is owned by Maka Sabanadze.
Racha Green Energy is directed and founded by Georgian citizen Davit Ugrelidze. Accordingly, these individuals and companies are the entities represented in the company’s ownership structure.
Where will spoil dumps be located, and how is waste managed?
Specially designated disposal sites have been identified for the placement of spoil material generated during construction. Detailed information on their location and arrangement is provided in the Environmental Impact Assessment Report, under Subsection 2.3.2.3.2, “SORGITI 2 HPP Spoil Disposal Site Design.”
Trees felled within the framework of the project will initially be temporarily stored within the construction corridor and will subsequently be transferred to the LEPL National Forestry Agency for management. The company will then purchase the timber from the state and provide it free of charge to residents of the valley, distributed by village.
Following completion of construction works, land reclamation will be carried out at the spoil disposal sites and other areas affected by construction. Restoration measures will include the planting and establishment of native tree and plant species. The company will be responsible for planting and subsequent maintenance, while the works will be carried out under the supervision of the relevant state authorities.
The project has a separate waste management plan, included in the annexes to the EIA Report under Subsection 1.3, “Waste Management Plan.” The assessment of potential impacts on air quality and other environmental components is presented in Chapter 5 of the EIA Report.
Environmental oversight is not limited to studies conducted prior to the start of construction. During both the construction and operational phases of the hydropower plants, various environmental components within the SORGITI 1 and SORGITI 2 corridors will be subject to periodic monitoring in accordance with the Environmental Monitoring Plan. This plan has been submitted to the Agency for approval.
What infrastructure and preventive measures will be implemented for the residents of the eight villages?
The project provides for a range of infrastructure, social, employment, safety, and environmental measures. The main areas include:
The geographical scope of the initiatives varies depending on their nature. Funding generated through property tax and seasonal road clearance benefit all villages in the valley.
Other infrastructure projects are planned for villages in the valley that are directly adjacent to the Jejora River.
The annual Social Assistance Fund covers five villages: Pipileti, Sorgiti, Onchevi, Kvedrula, and Iri.
Local Budget and Employment
- The company will pay approximately GEL 1,600,000 annually to the local budget in the form of property tax;
- During construction of the hydropower plants, approximately 100–150 local residents are expected to be employed in various positions;
- Once the hydropower plants become operational, approximately 40–50 people are expected to be employed on a permanent basis;
- Graduates in energy-related fields will have opportunities to work for the company, including in relevant managerial positions.
Social Support and Education
- Under the Social Assistance Fund, a total of GEL 100,000 will be allocated annually to five villages: Pipileti, Sorgiti, Onchevi, Kvedrula, and Iri. Each village will receive GEL 20,000 per year.
Funding will begin once construction is completed and the hydropower plants are commissioned, and will continue annually, indefinitely.
- A vocational training centre is planned to be established either at Pipileti Secondary School or at one of the schools in Oni, where interested individuals will be able to receive training in energy, as well as agriculture and livestock farming;
- Gold medal-winning school students and university students will be encouraged and supported;
- The company has already purchased a minibus to provide transportation for students and teachers of Pipileti Public School. The school will also be periodically supplied with necessary equipment and materials.
Roads and Village Infrastructure
- In coordination with the National Forestry Agency, roads and trails leading to village pastures, logging areas, and tourist locations will be constructed, rehabilitated, and improved;
- The company will provide year-round maintenance of internal village roads. During natural disasters or severe weather events, the company’s heavy machinery will be available for road clearing and widening;
- Drinking water intake facilities and main electricity transmission lines will be rehabilitated and improved;
- Riverbank protection works will be carried out where necessary;
- Unused and dilapidated buildings will be dismantled.
Internet and Safety
- Fiber-optic internet infrastructure will be introduced throughout the valley;
- A video surveillance system covering the valley is planned, which will help improve public safety and prevent illegal fishing in the river.
River, Fish and Tourism Infrastructure
- The river will be stocked with trout fry;
- If there is demand, trout ponds will be developed to support trout farming activities;
- Existing bathing areas will be improved and new locations will be identified;
- Rafting and camping areas will be developed, contributing to the growth of tourism infrastructure.
Community and Cultural Spaces
- The project provides for the restoration and improvement of religious and ceremonial sites, old community clubs, libraries, and sports grounds;
- In cooperation with the Patriarchate, the local diocese, and local residents, the construction, restoration, or rehabilitation of churches in Pipileti, Onchevi, and Iri is envisaged.
These measures are intended to improve the valley’s day-to-day infrastructure while also supporting employment, education, safety, tourism development, environmental protection, and social welfare.